After a contract has been signed, only the Board of Education can issue a change order. This holds true whether or not the change would add to the cost of the project.
Only the Business Administrator/Board Secretary may, in situations which would adversely affect the construction schedule, approve a change order and present the change to the Board of Education at the next scheduled meeting.
Date: April 14, 1986
December 10, 2001 First Reading
January 14, 2002 Approved
Legal Reference:
N.J.A.C. 6:20-8.3 Change orders
Key Words
Change Orders
|